Fécamp Offshore Wind Farm

PROJEKTS

The Fécamp offshore wind farm is the 1st wind farm in Normandy. It was initiated by Skyborn in 2007.

Skyborn, in consortium with EDF Renewables and EIH S.à. r.l, (a subsidiary of Enbridge Inc. and Canada Pension Plan Investment Board (CPP Investments)) is proud to have won the 2012 tender for the development, construction and operation of the Fécamp offshore wind farm.

The wind farm was officially commissioned in May 2024. The wind farm now supplies clean, green energy to more than 350,000 households (equivalent to 770,00 people).

Capacity

MW:

490

Overview

Data:

  • WTG71 x Siemens Gamesa (SWT-7.0-154)
  • Foundation typeGravity Based
  • Distance to shore13 – 24km
  • StatusCommissioned in 2024
  • Households provided with clean energy350,000
MILESTONES

Development

2007-2015

Milestones 2 / 0

2007

  • Starting point for local consultations with stakeholders, environmental & professional organizations.

2007 - 2011

  • Creation of a local consultation committee, in charge defining the most accepted project. Launch technical & environmental studies.

2011 & 2012

  • Launch of the call for tender phase by French state. In 2012, the consortium formed by EDF Renewables, EIH (Enbridge & CPP Investments) and Skyborn is awarded. 2013: Public debate.

2013

  • Public debate.

2014

  • Permit application to the relevant authorities.

2015

  • Installation of the measuring wind mast and approval from Public Debate Commission for Fécamp offshore farm.
MILESTONES

Construction

2020-2024

Milestones 2 / 0

June 2020

  • Official launch of the wind farm construction & sites.

Feb. 2020

  • Completion of the 1st gravity-based foundation.

June 2022

  • Opening of the O&M base.

August 2022

  • Installation of the offshore substation.

From summer 2022

  • Installation of the 71 gravity-based foundations at sea.

Summer 2023

  • Installation of the 1st turbine, out 71.

May 2024

  • Commissioning and grid connection of all 71 wind turbines